Royal Netherlands Institute for Sea Research
Royal Netherlands
Institute for Sea Research

RV Wim Wolff

15 November 2019
Final specifications
RV Wim Wolff, the replacement of RV Navicula, has been designed by Conoship.
30 April 2020
Start tender shipyard
A careful selection process is made to select the shipyard for the replacement of RV Navicula. The new vessel will be named after Wadden ecologist Wim Wolff, who played an instrumental role in international mudflat research.
26 January 2021
Contract signing
After a careful selection process, Thecla Bodewes Shipyards in the north of the Netherlands was chosen to construct the replacement of the RV Navicula. They will shortly begin with the construction process that will take about two years.
31 January 2021
Video RV Wim Wolff
Watch the video of RV Wim Wolff: " Taking science to the heart of the Wadden Sea" with Katja Philippart and other who talk about WIm Wolff, the importance of Wadden sea monitoring and why the new ships are essential for Wadden sea research.
February 2021
#1 The construction process
The construction of RV WIm Wolff will take 24 months from the signing of the contract and consists of several phases: Making the final design, Construction and Fitting out of the hull and finally commissioning and trial runs.
March 2021
#2 TB Shipyards
Thecla Bodewes Shipyards, consists of four shipyards in Stroobos, Kampen, Meppel and Harlingen with 120 employees. It is specialised in challenging construction projects and always aims to realise a design in a sustainable and innovative manner.
April 2021
#3 Project management
To ensure good communications and the smooth construction of the RV Wim Wolff, a project management team has been created with representatives from the client and the shipyard. This team will meet every two weeks, with additional technical meetings as necessary
01 June 2021
Sucessful modeltests
On Tuesday 1st of June and Wednesday 2nd of June occurred at MARIN premises in Wageningen the powering propulsion and resistance model tests using a real scale model of the RV Wim Wolff. These powering model tests are meant to verify the calculated needed power.
25 June 2021
#4 The hull builders
To accelerate the construction time, Thecla Bodewes Shipyards has decided to divide the construction of the hull in two sections by two different shipbuilders. KB Alubouw in Makkum will build part of the hull in collaboration with N. Dijkstra Metaalbewerking in Harlingen.
28 July 2021
#5 Model testing at Marin
Two model tests are planned for RV Wim Wolff: speed and sea behaviour. A different scale model is made for each type of test. The speed tests were carried out first, in June, in the towing tank at MARIN in Wageningen.
01 September 2021
#6 Ferry box
One major scientific innovation on board the RV Wim Wolff is the installation of a ‘ferry box’; an automated system for the continuous measurement, display and storage of various water parameters.
22 September 2021
#7 Sea handling tests
After the speed tests, the second series of model tests were intended to monitor the RV Wim Wolff’s sea handling. A specially designed 6-meter model of the vessel tested two different aspects of sea handling under the influence of wave force and direction.
21 October 2021
#8 Start hull construction
The contract signed by TBS stipulates that before work can begin on the hull, the client must give written approval for both the definitive, or ‘basic’ design and for the results of the drag tank tests conducted by MARIN.
09 November 2021
Festive keel laying
On 9 November 2021, the festive keel laying of the new national Wadden and Delta research vessel, RV Wim Wolff, took place at N. Dijkstra Metaalbewerking in Harlingen. Tradition has it that a coin is welded onto the keel beam 'for good luck'.
10 November 2021
#9 Hull contruction
The hull will be built in 6-meter sections that are welded together to form the finished vessel. It will be built in ‘reverse’ order: the bottom of each section will be assembled first, then the section will be rotated to finish the construction.
13 December 2021
#10 Keel laying ceremony
The keel of the RV Wim Wolff was laid at N. Dijkstra Metaalbewerking in Harlingen on 9 November. In her welcome greeting, Thecla Bodewes recalled the vital role Alex Colfino played in the contract negotiations and in supervising the construction of the RV Wim Wolff.
31 December 2021
#11 Joining sections
Due to the size of the RV Wim Wolff, the hull has been assembled in individual sections, which will be joined together at a centralised location. TBSY has contracted with three shipbuilders in the region for the construction of the various hull sections
31 January 2022
#12 Large building blocks
Three of the 20 sections were complete or nearing completion by late December, and since then another three have been completed and construction has begun on another three. All sections will be joined togehter at N.Dijkstra in Harlingen.
14 March 2022
#13 First ring sections
The sections will be joined together in two phases. During the first phase, the bottom sections (labelled ‘300’ sections) will be joined to the top sections (the ‘400’ sections) to form a ring structure.
14 April 2022
#14 Puzzle of pipelines
Before building the sections, all of the functionalities had to be added to the design and the final hull design approved of. This ‘puzzle’ work included deciding on the definitive positions of the tanks, bushings and pipelines inside the vessel.
17 May 2022
#15 A- and J-frames
The 3-D details of the main cranes (the A- and J-frame) have been finalised and exhaustively inspected for functionality and safety.
15 June 2022
#16 Maximum passage
The vessel will transit between the Wadden Sea and the waters of Zeeland via the coastal zone. During bad weather, an alternative inland waterway route is available with a maximum passage under bridges of 8.9 meters.
12 July 2022
#17 Hull construction
Almost all of the individual sections are now under construction, and the hull should be complete after the summer so that the vessel can be moved to the final construction location at TBSY.
10 August 2022
#18 Taking shape
The hull is beginning to take shape, and the completion diagram is gradually shifting from white (sections not yet under construction) to green (sections under construction and/or complete) and orange (sections joined to the hull.